Attic Ambush
| |

Several months after occupancy: no insulation in the attic.
|
A new Fort Collins home, built by a large production
builder, was completed in mid-summer 1999. It was a simple design: a compact
ranch with a finished basement, totaling 1900 square feet. The home was
purchased by the parents of a Colorado State University student as an investment
and place for their daughter and her college roommates to live.
The occupants moved into their new home in August and
immediately noticed major comfort problems. All main floor rooms consistently
ran too warm—78 degrees Fahrenheit with the air conditioner running virtually
full time. Meanwhile, the basement bedroom was consistently too cold—63 degrees
even with some supply registers closed. In response to complaints, the builder
sent their heating contractor back twice to solve the problem. Some limited duct
sealing and minor adjustments to the air conditioning system improved comfort
only marginally. The occupants concluded, “Oh well, that must be the way new
homes are” and decided to live with the problems. But in October they were
puzzled that the air conditioner would run during the day, then the furnace
would run at night. By December, they had the builder back to check on their
furnace, because the main level was never really comfortable (even when the air
temperature registered 68 degrees), while the basement was too hot (75 degrees).
The problem, quickly discovered in a January 2000 site
visit by City staff: no attic insulation. Yet the code-required Insulation
Disclosure form, on file at B&Z, signed by the insulation contractor,
documented 12 inches of an unidentified insulation material, rated R-38, in the
attic. Once the builder was notified of the problem, insulation was installed
within 48 hours. The comfort of the home improved dramatically with this change.
|

This information was submitted by the builder to the City of Fort Collins
Building and Zoning Department as part of the requirements to obtain a
Certificate of Occupancy for the Completed home. It was signed by the
insulation contractor.
|
|
The missing insulation was clearly an oversight, never
caught by quality control. Apparently neither the insulation contractor, the
builder, nor the City’s inspectors ever looked in the attic. There was also
clearly a major failure in the builder’s callback response; the problem was not
identified in at least three return trips to the house. As a result, the owners
paid an estimated $150 more than necessary to heat and cool the home. The
occupants put up with miserable comfort for six months and were generally jaded
about new homes. The builder’s site superintendent wasted time on the phone
dealing with callbacks, and the heating contractor spent unproductive time
visiting and trying to fix problems. The builder had already paid the insulator
for a job never performed.
The missing attic insulation was the biggest single problem
in this home – one that fortunately was easy to remedy. Yet City staff (using a
blower door, infrared camera, pressure gauge and smoke source) compiled a list
of other problems:
-
Whole house air leakage. A blower-door test
showed that the house was about one-third leakier than the average Fort
Collins new home. Numerous leaks to the attic were observed, including
connections between the attic and return air duct system.
-
Thermal bypasses. One wall, framed 12” thick
to avoid building a ledge at the top of the foundation, provided air space for
thermal convection and leakage connections to the attic; this reduced the
effective R-value of the wall insulation. A decorative archway in an interior
partition wall created a framing cavity totally open to the attic; cold attic
air drops into this space during the winter, bypassing the attic insulation.
-
Exposed fiberglass. The basement walls were
finished by framing out a 2x4 wall and insulating with unfaced fiberglass
batts. Most of the space was finished with drywall, however the mechanical
room had no wallboard or other protective cover to contain the insulation’s
glass fibers. This was a health and safety concern and violation of the code’s
Insulation Guidelines.
-
Duct design. The home’s supply ductwork
system was not effectively designed; by placing a supply takeoff immediately
above the supply riser, the basement bedroom received far more supply air than
it needed to be comfortable; as a result, it ran too warm when the furnace
operated and too cold when the air conditioning was on.
-
Combustion safety. The furnace and water
heater were isolated in a mechanical room. Within the room were two major
sources of depressurization that could potentially backdraft the combustion
equipment: a missing section of panning on a floor joist cavity that served as
part of the return air system; and a combustion air duct that ran vertically
from the basement to a termination above the roof (and acted like a chimney).
- Bath
fan. The typical low-end bath fan was rendered even less effective
by the ductwork that was used to vent it. The duct had a 180-degree bend at
the fan outlet (reducing flow significantly) and was very tenuously attached
to the fan outlet with tape alone.
|